Development · Suffolk
Ten-property development saved after knotweed strike
After hitting knotweed once four foundations were laid, a developer faced losing the entire site. We redesigned the floor footprint of the remaining six properties to encapsulate the contaminated area, screened over 70 tonnes of soil and worked with the local authority to certify the site.
We didn't lose a single plot — the build resumed inside the same calendar quarter.
- Sector
- Residential development
- Brief
- Stop-work mid-build
- Outcome
- Site certified, build resumed